Date: December 05, 2023
Subject: Concrete Work – Community Wide Starting TOMORROW – ACTION REQUIRED
Good Afternoon Queen’s Landing Residents,
 
Just a reminder that concrete work for walkways is to begin tomorrow.  The contractor was not able to get out to mark areas by today, however, they will be out early in the morning to mark the areas before 7 am.  Below is an overview of areas where work will be completed. Some are walkways to units and other are general areas of the main sidewalk:
 
 Address Demo Pouring Clean Up
26C Queen Anne Way 12/6/2023 12/6/2023  12/8/2024
26f Queen Anne Way 12/6/2023 12/6/2023  12/8/2025
31A Queen Anne Way 12/6/2023 12/6/2023  12/8/2024
31b Queen Anne Way 12/6/2023 12/6/2023  12/8/2025
31C Queen Anne Way 12/6/2023 12/6/2023  12/8/2026
31K Queen Anne Way 12/6/2023 12/6/2023  12/8/2027
34B Queen Anne Way 12/6/2023 12/6/2023  12/8/2028
34C Queen Anne Way 12/6/2023 12/6/2023  12/8/2029
35C Queen Anne Way 12/6/2023 12/6/2023  12/8/2030
36F Queen Anne Way 12/6/2023 12/6/2023  12/8/2031
48B Queen Guinevere 12/6/2023 12/6/2023  12/8/2024
48c Queen Guinevere Way 12/6/2023 12/6/2023  12/8/2025
48D Queen Guinevere Way 12/6/2023 12/6/2023  12/8/2026
49G Queen Guinevere Way 12/6/2023 12/6/2023  12/8/2027
49H Queen Guinevere Way 12/6/2023 12/6/2023  12/8/2028
02b Queen Victoria Court 12/6/2023  12/7/2023   12/8/2023 
03E Queen Victoria Court 12/6/2023  12/7/2023   12/8/2023 
03F Queen Victoria Court 12/6/2023  12/7/2023   12/8/2023 
03G Queen Victoria Court 12/6/2023  12/7/2023   12/8/2023 
03H Queen Victoria Court 12/6/2023  12/7/2023   12/8/2023 
06G Queen Victoria Way 12/6/2023  12/7/2023   12/8/2023 
07A Queen Victoria Way 12/6/2023  12/7/2023   12/8/2023 
27f Queen Mary Court 12/6/2023  12/7/2023   12/8/2023 
29a Queen Mary Court 12/6/2023  12/7/2023   12/8/2023 
42A Queen Catherine Way 12/6/2023  12/7/2023   12/8/2023 
42F Queen Catherine Way 12/6/2023  12/7/2023   12/8/2023 
42G Queen Catherine Way 12/6/2023  12/7/2023   12/8/2023 
43A Queen Neva Court 12/6/2023  12/7/2023   12/8/2023 
43D Queen Neva Court 12/6/2023  12/7/2023   12/8/2023 
44a Queen Neva Court 12/6/2023  12/7/2023   12/8/2023 
44b Queen Neva Court 12/6/2023  12/7/2023   12/8/2023 
44H Queen Neva Court 12/6/2023  12/7/2023   12/8/2023 
45G Queen Neva Court 12/6/2023  12/7/2023   12/8/2023 
54b Queen Caroline Court 12/6/2023  12/7/2023   12/8/2023 
       
*Any area demo’d but not poured will be coned and/or caution taped off with pouring to occur the following day.
 
MARKING AREAS
  • Early morning, 12/6/2023, contractor will mark the areas where work is to be completed. Please take note where sections have been marked for replacement.  On the day work is scheduled please do not park in the two spaces located directly in front of each area marked.  The contractor needs this area for their equipment and this also protects your vehicle from possible damage.
DEMO
  • All marked locations will be demo’d on 12/6/2023.
POURING NEW CONCRETE
  • Locations on Queen Anne Way and Queen Guinevere Way 12/6/2023*
  • All other locations 12/7/2023*
*Any area demo’d and not having concrete poured the same day will be coned and/or caution taped off with pouring to occur the following day.
 
CLEAN UP AND DEMOBILIZATION
  • 12/8/2023 all locations
If you have questions regarding this notice or the project in general, please contact the office at 410-643-5192 or at [email protected]. If you have an area you feel needs to be addressed please submit a maintenance request so that the area can be looked at for the next round of concrete to be completed in 2024.